Proposal for Healthcare Facility Design- Sequential Implementation Plan and Timeline
Task Name | Start Date | End Date | Duration |
Location Search | 7th June | 7th Aug | 3 months |
Land Search | 7th Aug | 30th Sep | 53 days |
Prerequisite evaluations | 30th Sep | 7th Nov | 1 week |
Purchase offer negotiations | 7th Nov | 14th Nov | 1 week |
Closing Process | 14th Nov | 15th Nov | 1 week |
Document recordation | 15th Nov | 15th Dec | 1 month |
Construction | 15th Dec | 30th Sep | 9.5 months |
Site preparation | 15th Dec | 15-Jan | 1 month |
Site partitioning | 15th Jan | 31-Jan | 2 weeks |
Building a water reservoir | 31-Jan | 15th Feb | 2 weeks |
Facility building | 1st Mar | 30th Aug | 5 months |
Building a recreation facility | 30th Jun | 30th Sep | 3 months |
Equipment and Instrument Installation | 10th Oct | 31st Oct | 3 weeks |
Installation of kitchen equipment. | 10th Oct | 17th Oct | 1 week |
Installation of laundry equipment. | 17th Oct | 24th Oct | 1 week |
Bed installation | 24th Oct | 31-Oct | 1 week |
Standby generator installation | 27th Oct | 30th Oct | 3 days |
Water tanks installation | 27th Oct | 30th Oct | 3 days |
Facility inspection | 1st Nov | 8th Nov | 1 week |
Lighting and plumbing inspections | 1st Nov | 8th Nov | 1 week |
Building finishes and floor space inspection | 1st Nov | 8th Nov | 1 week |
Launching | 8th Nov | 1oth Jan | 2 months |
Application for regulatory inspection and registration | 8th Nov | 8th Dec | 1 month |
Application for insurance credentialling | 10th Dec | 1st Jan | 21 days |
Staff recruitment and orientation | 1st Dec | 31-Dec | 1 month |
Resident recruitment | 1st Jan | N/A | Ongoing |
Grand opening | 10-Jan |
ORDER A PLAGIARISM-FREE PAPER HERE
We’ll write everything from scratch
Question
Scenario
Upper management has been watching and is impressed by the work you have done as project lead to gather information for this departmental expansion project. Your administrator passes along their request that you use your skills in project management to explain healthcare facility design project management by creating a proposal of what this project might look like. They want to know the sequentially ordered steps of implementation, including how long each step will take. Furthermore, as a salute to the remarkable job you have done, they are asking you to join the hospital’s services expansion committee as its facility planning expert.
Preparation
The Gantt chart is a widely accepted graphical tool for planning, presenting, and tracking complex projects. Use the information and template from Microsoft’s Present Your Data in a Gantt Chart in Excel site to learn how to develop a Gantt chart.
We have seen a proliferation of project planning software available for free, either on a trial or basics-only basis. Research and choose a project planning software tool of your choice (e.g., Trello, ClickUp, and Monday.com). Choose 1 app that you can use as a demo for the services expansion committee.
Assessment Deliverable
PART 1 – Create a Gantt chart to display the relationships among the tasks to be completed. You might think back to the Week 2 Summary: Facility Selection and Research assignment on the five project process groups.
PART 2 – Use your chosen project planning software tool (Microsoft Excel, Trello, ClickUp, or Monday.com) to outline the planning, design, and construction of your facility. This must be an original design. The planning chart from your software needs to also be submitted.
Using a document as a medium to lay out your project proposal components, assemble your Gantt chart graphic and screenshots from your project planning software tool of the analysis of the flow of your completed facility project.
PART 3 -Summary – Include a 175- to 350-word APA formatted summary that explains your approach to your chosen healthcare facility design project management proposal including details on cultural compliance.